Sec. 25.118 Modifications not requiring prior authorization.
(a) Equipment in an authorized earth station may be replaced without
prior authorization or prior notification if the new equipment is
electrically identical to the existing equipment. Licensees must notify
the Commission using FCC Form 312, Main Form, within 30 days after the
new equipment is installed.
(b) A licensee providing service on a private carrier basis may
change its operations to common carrier status without obtaining prior
Commission authorization. The licensee must notify the Commission using
Form 312 within 30 days after the completed change to common carrier
status.
(c) Licensees may make changes to their authorized earth stations
without obtaining prior Commission authorization if frequency
coordination procedures, as necessary, are complied with in accordance
with Sec. 25.251, and the modification does not involve:
(1) An increase in EIRP or EIRP density (both main lobe and side
lobe);
(2) An increase in transmitted power;
(3) A change in coordinates of more than 1 second for stations
operating in C-Band or 10.95 to 11.7 GHz;
(4) A change in coordinates of 10 seconds or greater for stations
operating in Ku-band; or
(5) An addition to an antenna facility, including hub earth stations
and remote terminals, that is already licensed, except for VSAT remote
terminals.
(d) Licensees must notify the Commission using FCC Form 312 within
30 days after the modification is completed.
[ 62 FR 5928 , Feb. 10, 1997]
CiteFind - See documents on FCC website that
cite this rule
Want to support this service?
Thanks!
Report errors in
this rule. Since these rules are converted to HTML by machine, it's possible errors have been made. Please
help us improve these rules by clicking the Report FCC Rule Errors link to report an error.