FCC 25.133
Revised as of
Goto Year:1996 |
1998
Sec. 25.133 Period of construction; certification of commencement of
operation.
(a) Each license for an earth station governed by this part shall
specify as a condition therein the period in which construction of
facilities must be completed and station operation commenced.
Construction of the earth station must be completed and the station must
be brought into regular operation within 12 months from the date of the
construction permit and/or license grant except as may be otherwise
determined by the Commission for any particular application.
(b) Each license for a transmitting earth station included in this
part shall also specify as a condition therein that upon the completion
of construction, each licensee must file with the Commission a
certification containing the following information: The name of the
licensee; file number of the application; call sign of the antenna; date
of the license; a certification that the facility as authorized has been
completed and that each antenna facility has been tested and is within 2
dB of the pattern specified in Sec. 25.209, Sec. 25.135 (NVNG MSS earth
stations), or Sec. 25.213 (1.6/2.4 GHz Mobile-Satellite Service earth
stations); the date on which the station became operational; and a
statement that the station will remain operational during the license
period unless the license is submitted for cancellation. For stations
authorized under Sec. 25.115(c) of this part (Large Networks of Small
Antennas operating in the 12/14 GHz bands) and Sec. 25.115(d) of this
part (User Transceivers in the Mobile-Satellite Service), a certificate
must be filed when the network is put into operation.
(c) If the facility does not meet the technical parameters set forth
in Sec. 25.209, a request for a waiver must be submitted and approved by
the Commission before operations may commence.
(d) Each receiving earth station licensed or registered pursuant to
Sec. 25.131 must be constructed and placed into service within 6 months
after coordination has been completed. Each licensee or registrant must
file with the Commission a certification that the facility is completed
and operating as provided in paragraph (b) of this section, with the
exception of certification of antenna patterns.
[ 56 FR 24016 , May 28, 1991, as amended at 58 FR 68059 , Dec. 23, 1993; 59 FR 53327 , Oct. 21, 1994]
Goto Section: 25.132 | 25.134
Goto Year: 1996 |
1998
CiteFind - See documents on FCC website that
cite this rule
Want to support this service?
Thanks!
Report errors in
this rule. Since these rules are converted to HTML by machine, it's possible errors have been made. Please
help us improve these rules by clicking the Report FCC Rule Errors link to report an error.
hallikainen.com
Helping make public information public