Sec. 74.833 Temporary authorizations.
(a) Special temporary authority may be granted for low power
auxiliary station operation which cannot be conducted in accordance with
Sec. 74.24. Such authority will normally be granted only for operations
of a temporary nature. Where operation is seen as likely on a continuing
annual basis, an application for a regular authorization should be
submitted.
(b) A request for special temporary authority for the operation of a
low power auxiliary station may be made by informal application, which
shall be filed with the Commission in Washington at least 10 days prior
to the date of the proposed operation: Provided, That, an application
filed within less than 10 days of the proposed operation may be accepted
upon a satisfactory showing of the reasons for the delay in submitting
the request.
(c) An informal request for special temporary authority requiring
payment of a fee shall be addressed to the FCC at Federal Communications
Commission, Broadcast Auxiliary Radio Services, P.O. Box 358700,
Pittsburgh, PA 15251-5700. An informal request for special temporary
authority not requiring payment of a fee shall be addressed to the FCC
at Federal Communications Commission, 1270 Fairfield Road, Gettysburg,
Pennsylvania 17325. All requests must include full particulars
including: Applicant's name, statement of eligibility, call letters of
associated broadcast station or stations, if any, name and address of
individual designated to receive the return telegram, type and
manufacturer of equipment, power output, emission, frequency or
frequencies proposed to be used, commencement and termination date,
location of proposed operation, and purpose for which request is made
including any particular justification.
(d) A request for special temporary authority shall specify a
frequency band consistent with the provisions of Sec. 74.802: Provided,
That, in the case of events of wide-spread interest and importance which
cannot be transmitted successfully on these frequencies, frequencies
assigned to other services may be requested upon a showing that
operation thereon will not cause interference to established stations:
And provided further, In no case will operation of a low power auxiliary
broadcast station be authorized on frequencies employed for the safety
of life and property.
(e) The user shall have full control over the transmitting equipment
during the period it is operated.
(f) Special temporary authority to permit operation of low power
auxiliary stations pending Commission action on an application for
regular authority will not normally be granted.
[ 42 FR 14729 , Mar. 16, 1977, as amended at 47 FR 9221 , Mar. 4, 1982; 47 FR 55939 , Dec. 14, 1982; 58 FR 19776 , Apr. 16, 1993]
CiteFind - See documents on FCC website that
cite this rule
Want to support this service?
Thanks!
Report errors in
this rule. Since these rules are converted to HTML by machine, it's possible errors have been made. Please
help us improve these rules by clicking the Report FCC Rule Errors link to report an error.