Sec. 95.83 Additional information for stations with antennas higher
than normally allowed.
(a) An applicant for a license for a new or modified GMRS system
seeking permission to have a land station antenna higher than normally
allowed (see Sec. 95.51) must:
(1) Request (on FCC Form 574) an antenna height greater than
normally allowed; and
(2) Notify the Federal Aviation Administration (on FAA Form 7460-1)
that the antenna would be higher than normally allowed.
(3) Register the structure by submitting FCC Form 854. The
requirements for antenna structure registration, painting, and lighting
are found in part 17 of this chapter.
(b) Each base station and each control station with an antenna
height greater than 6.1 meters (20 feet) must be separately identified
on Form 574 (see Secs. 95.25 (d) and (e) and 95.51(f)).
[48 1997 FR 35237 , Aug. 3, 1983, as amended at 53 FR 47716 , Nov. 25, 1988; 61 FR 4369 , Feb. 6, 1996]
CiteFind - See documents on FCC website that
cite this rule
Want to support this service?
Thanks!
Report errors in
this rule. Since these rules are converted to HTML by machine, it's possible errors have been made. Please
help us improve these rules by clicking the Report FCC Rule Errors link to report an error.