Sec. 2.938 Retention of records.
(a) For each equipment subject to the Commission's equipment authorization
standards, the responsible party shall maintain the records listed as
follows:
(1) A record of the original design drawings and specifications and all
changes that have been made that may affect compliance with the standards
and the requirements of Sec. 2.931.
(2) A record of the procedures used for production inspection and testing to
ensure conformance with the standards and the requirements of Sec. 2.931.
(3) A record of the test results that demonstrate compliance with the
appropriate regulations in this chapter.
(b) The provisions of paragraph (a) of this section shall also apply to a
manufacturer of equipment produced under the provisions of Sec. 2.929(b). The
retention of the records by the manufacturer under these circumstances shall
satisfy the grantee's responsibility under paragraph (a) of this section.
(c) The records listed in paragraph (a) of this section shall be retained
for one year for equipment subject to authorization under the certification
procedure or former type acceptance procedure, or for two years for
equipment subject to authorization under any other procedure, after the
manufacture of said equipment has been permanently discontinued, or until
the conclusion of an investigation or a proceeding if the responsible party
(or, under paragraph (b) of this section, the manufacturer) is officially
notified that an investigation or any other administrative proceeding
involving its equipment has been instituted.
(d) If radio frequency equipment is modified by any party other than the
original responsible party, and that party is not working under the
authorization of the original responsible party, the party performing the
modifications is not required to obtain the original design drawings
specified in paragraph (a)(1) of this section. However, the party performing
the modifications must maintain records showing the changes made to the
equipment along with the records required in paragraphs (a)(3) of this
section. A new equipment authorization may also be required. See, for
example, Sec. Sec. 2.909, 2.924, 2.933, and 2.1043.
[ 62 FR 10471 , Mar. 7, 1997, as amended at 63 FR 36599 , July 7, 1998]
CiteFind - See documents on FCC website that
cite this rule
Want to support this service?
Thanks!
Report errors in
this rule. Since these rules are converted to HTML by machine, it's possible errors have been made. Please
help us improve these rules by clicking the Report FCC Rule Errors link to report an error.