Goto Section: 22.1031 | 22.1037 | Table of Contents
FCC 22.1035
Revised as of October 1, 2005
Goto Year:2004 |
2006
Sec. 22.1035 Construction period.
The construction period (see Sec. 22.142) for offshore stations is 18 months.
Goto Section: 22.1031 | 22.1037
Goto Year: 2004 |
2006
CiteFind - See documents on FCC website that
cite this rule
Want to support this service?
Thanks!
Report errors in
this rule. Since these rules are converted to HTML by machine, it's possible errors have been made. Please
help us improve these rules by clicking the Report FCC Rule Errors link to report an error.
hallikainen.com
Helping make public information public