Goto Section: 22.1031 | 22.1037 | Table of Contents

FCC 22.1035
Revised as of October 1, 2005
Goto Year:2004 | 2006
Sec.  22.1035   Construction period.

   The construction period (see  Sec. 22.142) for offshore stations is 18 months.


Goto Section: 22.1031 | 22.1037

Goto Year: 2004 | 2006
CiteFind - See documents on FCC website that cite this rule

Want to support this service?
Thanks!

Report errors in this rule. Since these rules are converted to HTML by machine, it's possible errors have been made. Please help us improve these rules by clicking the Report FCC Rule Errors link to report an error.
hallikainen.com
Helping make public information public