Sec. 73.62 Directional antenna system tolerances.
(a) Each AM station operating a directional antenna must maintain the
indicated relative amplitudes of the antenna monitor currents within 5% of
the values specified therein. Directional antenna relative phase currents
must be maintained to within ±3 deg. of the values specified on the
instrument of authorization.
(b) Whenever the operating parameters of a directional antenna cannot be
maintained within the tolerances specified in paragraph (a) of this section,
the following procedures will apply:
(1) The licensee shall measure and log every monitoring point at least once
for each mode of directional operation. Subsequent variations in operating
parameters will require the remeasuring and logging of every monitoring
point to assure that the authorized monitoring point limits are not being
exceeded.
(2) Provided each monitoring point is within its specified limit, operation
may continue for a period up to 30 days before a request for Special
Temporary Authority (STA) must be filed, pursuant to paragraph (b)(4) of
this section, to operate with parameters at variance from the provisions of
paragraph (a) of this section.
(3) If any monitoring point exceeds its specified limit, the licensee must
either terminate operation within 3 hours or reduce power in accordance with
the applicable provisions of Sec. 73.1350(d), in order to eliminate any
possibility of interference or excessive radiation in any direction.
(4) If operation pursuant to paragraph (b)(3) of this section is necessary,
or before the 30 day period specified in paragraph (b)(2) of this section
expires, the licensee must request a Special Temporary Authority (STA) in
accordance with Sec. 73.1635 to continue operation with parameters at variance
and/or with reduced power along with a statement certifying that all
monitoring points will be continuously maintained within their specified
limits.
(5) The licensee will be permitted 24 hours to accomplish the actions
specified in paragraph (b)(1) of this section; provided that, the date and
time of the failure to maintain proper operating parameters has been
recorded in the station log.
(c) In any other situation in which it might reasonably be anticipated that
the operating parameters might vary out of tolerance (such as planned array
repairs or adjustment and proofing procedures), the licensee shall, before
such activity is undertaken, obtain an STA in accordance with Sec. 73.1635 in
order to operate with parameters at variance and/or with reduced power as
required to maintain all monitoring points within their specified limits.
[ 50 FR 30946 , July 31, 1985, as amended at 60 FR 55480 , Nov. 1, 1995; 66 FR 20755 , Apr. 25, 2001]
Goto Section: 73.61 | 73.68
Goto Year: 2004 |
2006
CiteFind - See documents on FCC website that
cite this rule
Want to support this service?
Thanks!
Report errors in
this rule. Since these rules are converted to HTML by machine, it's possible errors have been made. Please
help us improve these rules by clicking the Report FCC Rule Errors link to report an error.
hallikainen.com
Helping make public information public