Goto Section: 24.249 | 24.253 | Table of Contents

FCC 24.251
Revised as of October 1, 2006
Goto Year:2005 | 2007
Sec.  24.251   Dispute resolution under the Cost-Sharing Plan.

   Disputes arising out of the cost-sharing plan, such as disputes over the
   amount of reimbursement required, must be brought, in the first instance, to
   the clearinghouse for resolution. To the extent that disputes cannot be
   resolved by the clearinghouse, parties are encouraged to use expedited ADR
   procedures, such as binding arbitration, mediation, or other ADR techniques.

   [ 61 FR 29693 , June 12, 1996]


Goto Section: 24.249 | 24.253

Goto Year: 2005 | 2007
CiteFind - See documents on FCC website that cite this rule

Want to support this service?
Thanks!

Report errors in this rule. Since these rules are converted to HTML by machine, it's possible errors have been made. Please help us improve these rules by clicking the Report FCC Rule Errors link to report an error.
hallikainen.com
Helping make public information public