Sec. 24.251 Dispute resolution under the Cost-Sharing Plan.
Disputes arising out of the cost-sharing plan, such as disputes over the
amount of reimbursement required, must be brought, in the first instance, to
the clearinghouse for resolution. To the extent that disputes cannot be
resolved by the clearinghouse, parties are encouraged to use expedited ADR
procedures, such as binding arbitration, mediation, or other ADR techniques.
[ 61 FR 29693 , June 12, 1996]