Sec.  25.162   Cause for termination of interference protection.

   The protection from interference afforded by the registration of a receiving
   earth station shall be automatically terminated if:

   (a) The request for registration is not submitted to the Commission within 3
   months of the completion of the frequency coordination process, except as
   provided for in  Sec. 25.203;

   (b) The receiving earth station is not constructed and placed into service
   within 6 months after completion of coordination;

   (c) The Commission finds that the station has been used less than 50% of the
   time during any 12 month period;

   (d) The Commission finds that the station has been used for an unlawful
   purpose or otherwise in violation of the Commission's rules, regulations or
   policies;

   (e) The Commission finds that the actual use of the facility is inconsistent
   with what was set forth in the registrant's application; or

   (f) The Commission finds that the frequency coordination exhibit, upon which
   the granted registration is based, is incomplete or does not conform with
   established coordination procedures.


Goto Section: 25.161 | 25.163

Goto Year: 2005 | 2007
CiteFind - See documents on FCC website that cite this rule

Want to support this service?
Thanks!

Report errors in this rule. Since these rules are converted to HTML by machine, it's possible errors have been made. Please help us improve these rules by clicking the Report FCC Rule Errors link to report an error.
hallikainen.com
Helping make public information public