Goto Section: 73.3597 | 73.3601 | Table of Contents

FCC 73.3598
Revised as of October 1, 2006
Goto Year:2005 | 2007
Sec.  73.3598   Period of construction.

   (a) Each original construction permit for the construction of a new TV, AM,
   FM or International Broadcast; low power TV; TV translator; TV booster; FM
   translator; or FM booster station, or to make changes in such existing
   stations, shall specify a period of three years from the date of issuance of
   the original construction permit within which construction shall be
   completed and application for license filed. Each original construction
   permit for the construction of a new LPFM station shall specify a period of
   eighteen months from the date of issuance of the construction permit within
   which construction shall be completed and application for license filed.

   (b) The period of construction for an original construction permit shall
   toll when construction is prevented by the following causes not under the
   control of the permittee:

   (i) Construction is prevented due to an act of God, defined in terms of
   natural disasters (e.g., floods, tornados, hurricanes, or earthquakes) or

   (ii) the grant of the permit is the subject of administrative or judicial
   review (i.e., petitions for reconsideration and applications for review of
   the grant of a construction permit pending before the Commission and any
   judicial appeal of any Commission action thereon), or construction is
   delayed by any cause of action pending before any court of competent
   jurisdiction relating to any necessary local, state or federal requirement
   for the construction or operation of the station, including any zoning or
   environmental requirement.

   (c) A permittee must notify the Commission as promptly as possible and, in
   any event, within 30 days, of any pertinent event covered by paragraph (b)
   of this section, and provide supporting documentation. All notifications
   must be filed in triplicate with the Secretary and must be placed in the
   station's local public file.

   (d) A permittee must notify the Commission promptly when a relevant
   administrative or judicial review is resolved. Tolling resulting from an act
   of God will automatically cease six months from the date of the notification
   described in paragraph (c) of this section, unless the permittee submits
   additional notifications at six month intervals detailing how the act of God
   continues to cause delays in construction, any construction progress, and
   the steps it has taken and proposes to take to resolve any remaining
   impediments.

   (e) Any construction permit for which construction has not been completed
   and for which an application for license has not been filed, shall be
   automatically forfeited upon expiration without any further affirmative
   cancellation by the Commission.

   [ 63 FR 70050 , Dec. 18, 1998, as amended at  65 FR 7648 , Feb. 15, 2000;  68 FR 12761 , Mar. 17, 2003;  69 FR 53352 , Sept. 1, 2004]


Goto Section: 73.3597 | 73.3601

Goto Year: 2005 | 2007
CiteFind - See documents on FCC website that cite this rule

Want to support this service?
Thanks!

Report errors in this rule. Since these rules are converted to HTML by machine, it's possible errors have been made. Please help us improve these rules by clicking the Report FCC Rule Errors link to report an error.
hallikainen.com
Helping make public information public