Sec. 80.921 Proof of capacity.
(a) When directed by a representative of the Commission the vessel must
prove by demonstration as prescribed in paragraphs (b), (c), (d) and (e) of
this section, that the requirements of Sec. 80.919 are met.
(b) Proof of the ability of a storage battery used as a main or reserve
power supply to operate over the 3-hour period established by a discharge
test over the prescribed period of time, when supplying power at the voltage
required for an electrical loss as prescribed by paragraph (d) of this
section.
(c) When the required power supply consists of an engine-driven generator,
proof of the adequacy of the engine fuel supply to operate the unit over the
3-hour period of time may be established by using as a basis the fuel
consumption during a 1 hour period when supplying power, at the voltage
required for operating an electrical load as prescribed by paragraph (d) of
this section.
(d) In determining the required electrical load the following formula must
be used:
(1) One-half of the current of the required transmitter at its rated output
power; plus
(2) Current of the required receiver; plus
(3) Current of electric light, if required by Sec. 80.925; plus
(4) The sum of the current of all other loads the reserve power supply may
provide in time of emergency.
(e) At the conclusion of the test specified in paragraphs (b) and (c) of
this section, no part of the main or reserve power supply must have an
excessive temperature rise, nor must the specific gravity or voltage of any
storage battery be below the 90 percent discharge point.
CiteFind - See documents on FCC website that
cite this rule
Want to support this service?
Thanks!
Report errors in
this rule. Since these rules are converted to HTML by machine, it's possible errors have been made. Please
help us improve these rules by clicking the Report FCC Rule Errors link to report an error.