§ 54.313 Annual reporting requirements for high-cost recipients.
(a) Any recipient of high-cost support shall provide:
(1) A progress report on its five-year service quality improvement plan
pursuant to § 54.202(a), including maps detailing its progress towards
meeting its plan targets, an explanation of how much universal service
support was received and how it was used to improve service quality,
coverage, or capacity, and an explanation regarding any network
improvement targets that have not been fulfilled in the prior calendar
year. The information shall be submitted at the wire center level or
census block as appropriate;
(2) Detailed information on any outage in the prior calendar year, as
that term is defined in 47 CFR 4.5, of at least 30 minutes in duration
for each service area in which an eligible telecommunications carrier
is designated for any facilities it owns, operates, leases, or
otherwise utilizes that potentially affect
(i) At least ten percent of the end users served in a designated
service area; or
(ii) A 911 special facility, as defined in 47 CFR 4.5(e).
(iii) Specifically, the eligible telecommunications carrier's annual
report must include information detailing:
(A) The date and time of onset of the outage;
(B) A brief description of the outage and its resolution;
(C) The particular services affected;
(D) The geographic areas affected by the outage;
(E) Steps taken to prevent a similar situation in the future; and
(F) The number of customers affected.
(3) The number of requests for service from potential customers within
the recipient's service areas that were unfulfilled during the prior
calendar year. The carrier shall also detail how it attempted to
provide service to those potential customers;
(4) The number of complaints per 1,000 connections (fixed or mobile) in
the prior calendar year;
(5) Certification that it is complying with applicable service quality
standards and consumer protection rules;
(6) Certification that the carrier is able to function in emergency
situations as set forth in § 54.202(a)(2);
(7) The company's price offerings in a format as specified by the
Wireline Competition Bureau;
(8) The recipient's holding company, operating companies, affiliates,
and any branding (a “dba,” or “doing-business-as company” or brand
designation), as well as universal service identifiers for each such
entity by Study Area Codes, as that term is used by the Administrator.
For purposes of this paragraph, “affiliates” has the meaning set forth
in section 3(2) of the Communications Act of 1934, as amended;
(9) Beginning April 1, 2013. To the extent the recipient serves Tribal
lands, documents or information demonstrating that the ETC had
discussions with Tribal governments that, at a minimum, included:
(i) A needs assessment and deployment planning with a focus on Tribal
community anchor institutions;
(ii) Feasibility and sustainability planning;
(iii) Marketing services in a culturally sensitive manner;
(iv) Rights of way processes, land use permitting, facilities siting,
environmental and cultural preservation review processes; and
(v) Compliance with Tribal business and licensing requirements. Tribal
business and licensing requirements include business practice licenses
that Tribal and non-Tribal business entities, whether located on or off
Tribal lands, must obtain upon application to the relevant Tribal
government office or division to conduct any business or trade, or
deliver any goods or services to the Tribes, Tribal members, or Tribal
lands. These include certificates of public convenience and necessity,
Tribal business licenses, master licenses, and other related forms of
Tribal government licensure.
(10) Beginning July 1, 2013. A letter certifying that the pricing of
the company's voice services is no more than two standard deviations
above the applicable national average urban rate for voice service, as
specified in the most recent public notice issued by the Wireline
Competition Bureau and Wireless Telecommunications Bureau; and
(11) Beginning July 1, 2013. The results of network performance tests
pursuant to the methodology and in the format determined by the
Wireline Competition Bureau, Wireless Telecommunications Bureau, and
Office of Engineering and Technology and the information and data
required by this paragraphs (a)(1) through (7) of this section
separately broken out for both voice and broadband service.
(b) In addition to the information and certifications in paragraph (a)
of this section, any recipient of incremental CAF Phase I support
pursuant to § 54.312(b) shall provide:
(1) In its next annual report due after two years after filing a notice
of acceptance of funding pursuant to § 54.312(b), a certification that
the company has deployed to no fewer than two-thirds of the required
number of locations; and
(2) In its next annual report due after three years after filing a
notice of acceptance of funding pursuant to § 54.312(b), a
certification that the company has deployed to all required locations
and that it is offering broadband service of at least 4 Mbps downstream
and 1 Mbps upstream, with latency sufficiently low to enable the use of
real-time communications, including Voice over Internet Protocol, and
with usage caps, if any, that are reasonably comparable to those in
urban areas.
(c) In addition to the information and certifications in paragraph (a)
of this section, price cap carriers that receive frozen high-cost
support pursuant to § 54.312(a) shall provide:
(1) By July 1, 2013. A certification that frozen high-cost support the
company received in 2012 was used consistent with the goal of achieving
universal availability of voice and broadband;
(2) By July 1, 2014. A certification that at least one-third of the
frozen-high cost support the company received in 2013 was used to build
and operate broadband-capable networks used to offer the provider's own
retail broadband service in areas substantially unserved by an
unsubsidized competitor;
(3) By July 1, 2015. A certification that at least two-thirds of the
frozen-high cost support the company received in 2014 was used to build
and operate broadband-capable networks used to offer the provider's own
retail broadband service in areas substantially unserved by an
unsubsidized competitor; and
(4) By July 1, 2016 and in subsequent years. A certification that all
frozen-high cost support the company received in the previous year was
used to build and operate broadband-capable networks used to offer the
provider's own retail broadband service in areas substantially unserved
by an unsubsidized competitor.
(d) In addition to the information and certifications in paragraph (a)
of this section, beginning July 1, 2013, price cap carriers receiving
high-cost support to offset reductions in access charges shall provide
a certification that the support received pursuant to § 54.304 in the
prior calendar year was used to build and operate broadband-capable
networks used to offer provider's own retail service in areas
substantially unserved by an unsubsidized competitor.
(e) In addition to the information and certifications in paragraph (a)
of this section, any recipient of CAF Phase II support shall provide:
(1) In the calendar year no later than three years after implementation
of CAF Phase II. A certification that the company is providing
broadband service to 85% of its supported locations at actual speeds of
at least 4 Mbps downstream/1 Mbps upstream, with latency suitable for
real-time applications, including Voice over Internet Protocol, and
usage capacity that is reasonably comparable to comparable offerings in
urban areas as determined in an annual survey.
(2) In the calendar year no later than five years after implementation
of CAF Phase II. A certification that the company is providing
broadband service to 100% of its supported locations at actual speeds
of at least 4 Mbps downstream/1 Mbps upstream, and a percentage of
supported locations, to be specified by the Wireline Competition
Bureau, at actual speeds of at least 6 Mbps downstream/1.5 Mbps
upstream, with latency suitable for real-time applications, including
Voice over Internet Protocol, and usage capacity that is reasonably
comparable to comparable offerings in urban areas as determined in an
annual survey.
(3) Beginning July 1, 2014. A progress report on the company's
five-year service quality plan pursuant to § 54.202(a), including the
following information:
(i) A letter certifying that it is meeting the interim deployment
milestones as set forth, and that it is taking reasonable steps to meet
increased speed obligations that will exist for all supported locations
at the expiration of the five-year term for CAF Phase II funding; and
(ii) The number, names, and addresses of community anchor institutions
to which the ETC newly began providing access to broadband service in
the preceding calendar year.
(f) In addition to the information and certifications in paragraph (a)
of this section, any rate-of-return carrier shall provide:
(1) Beginning July 1, 2014. A progress report on its five-year service
quality plan pursuant to § 54.202(a) that includes the following
information:
(i) A letter certifying that it is taking reasonable steps to provide
upon reasonable request broadband service at actual speeds of at least
4 Mbps downstream/1 Mbps upstream, with latency suitable for real-time
applications, including Voice over Internet Protocol, and usage
capacity that is reasonably comparable to comparable offerings in urban
areas as determined in an annual survey, and that requests for such
service are met within a reasonable amount of time; and
(ii) The number, names, and addresses of community anchor institutions
to which the ETC newly began providing access to broadband service in
the preceding calendar year.
(2) Privately held rate-of-return carriers only. A full and complete
annual report of the company's financial condition and operations as of
the end of the preceding fiscal year, which is audited and certified by
an independent certified public accountant in a form satisfactory to
the Commission, and accompanied by a report of such audit. The annual
report shall include balance sheets, income statements, and cash flow
statements along with necessary notes to clarify the financial
statements. The income statements shall itemize revenue, including
non-regulated revenue, by its sources. In lieu of filing this annual
report, any ETC that files annual financial reports with the Rural
Utilities Service may instead file a copy of its report to the Rural
Utilities Service.
(g) Areas with No Terrestrial Backhaul. Carriers without access to
terrestrial backhaul that are compelled to rely exclusively on
satellite backhaul in their study area must certify annually that no
terrestrial backhaul options exist. Any such funding recipients must
certify they offer broadband service at actual speeds of at least 1
Mbps downstream and 256 kbps upstream within the supported area served
by satellite middle-mile facilities. To the extent that new terrestrial
backhaul facilities are constructed, or existing facilities improve
sufficiently to meet the relevant speed, latency and capacity
requirements then in effect for broadband service supported by the CAF,
within twelve months of the new backhaul facilities becoming
commercially available, funding recipients must provide the
certifications required in paragraphs (e) or (f) of this section in
full. Carriers subject to this paragraph must comply with all other
requirements set forth in the remaining paragraphs of this section.
(h) Additional voice rate data. (1) All incumbent local exchange
carrier recipients of high-cost support must report all of their rates
for residential local service for all portions of their service area,
as well as state fees as defined pursuant to § 54.318(e), to the extent
the sum of those rates and fees are below the rate floor as defined in
§ 54.318, and the number of lines for each rate specified. Carriers
shall report lines and rates in effect as of June 1.
(2) In addition to the annual filing, local exchange carriers may file
updates of their rates for residential local service, as well as state
fees as defined pursuant to § 54.318(e), on January 2 of each year. If
a local exchange carrier reduces its rates and the sum of the reduced
rates and state fees are below the rate floor as defined in § 54.318,
the local exchange carrier shall file such an update. For the update,
carriers shall report lines and rates in effect as of December 1.
(j) Filing deadlines. In order for a recipient of high-cost support to
continue to receive support for the following calendar year, or retain
its eligible telecommunications carrier designation, it must submit the
annual reporting information required by this section no later than
July 1, 2012, except as otherwise specified in this section to begin in
a subsequent year, and thereafter annually by July 1 of each year.
Eligible telecommunications carriers that file their reports after the
July 1 deadline shall receive support pursuant to the following
schedule:
(1) Eligible telecommunication carriers that file no later than October
1 shall receive support for the second, third and fourth quarters of
the subsequent year.
(2) Eligible telecommunication carriers that file no later than January
1 of the subsequent year shall receive support for the third and fourth
quarters of the subsequent year.
(3) Eligible telecommunication carriers that file no later than April 1
of the subsequent year shall receive support for the fourth quarter of
the subsequent year.
(k) This section does not apply to recipients that solely receive
support from the Phase I Mobility Fund.
[ 76 FR 73873 , Nov. 29, 2011, as amended at 77 FR 14302 , Mar. 9, 2012;
77 FR 30914 , May 24, 2012]
Effective Date Note: At 76 FR 73873 , Nov. 29, 2011, § 54.313 was
revised. Paragraphs (a)(7) through (a)(11) and paragraphs (c) through
(g) contain information collection and recordkeeping requirements and
will not become effective until approval has been given by the Office
of Management and Budget.
Effective Date Note: At 77 FR 14302 , Mar. 9, 2012, § 54.313 was
amended. Paragraphs (a)(9) and (f)(2) contain information collection
and recordkeeping requirements and will not become effective until
approval has been given by the Office of Management and Budget.
Effective Date Note: At 77 FR 30914 , May 24, 2012, § 54.313 was
amended. Paragraph (h) contains information collection and
recordkeeping requirements and will not become effective until approval
has been given by the Office of Management and Budget.
return arrow Back to Top
Goto Section: 54.312 | 54.314
Goto Year: 2011 |
2013
CiteFind - See documents on FCC website that
cite this rule
Want to support this service?
Thanks!
Report errors in
this rule. Since these rules are converted to HTML by machine, it's possible errors have been made. Please
help us improve these rules by clicking the Report FCC Rule Errors link to report an error.
hallikainen.com
Helping make public information public