Goto Section: 25.163 | 25.165 | Table of Contents
FCC 25.164
Revised as of October 1, 2014
Goto Year:2013 |
2015
§ 25.164 Milestones.
(a) Licensees of geostationary orbit satellite systems other than DBS
and DARS satellite systems, including GSO MSS satellite systems,
licensed on or after August 27, 2003 will be required to comply with
the schedule set forth in paragraphs (a)(1) through (a)(4) of this
section in implementing their satellite systems, unless a different
schedule is established by Title 47, Chapter I, or by Commission Order,
or by Order adopted pursuant to delegated authority. These dates are to
be measured from the date the license is issued.
(1) One year: Enter into a binding non-contingent contract to construct
the licensed satellite system.
(2) Two years: Complete the critical design review of the licensed
satellite system.
(3) Three years: Begin the construction of the satellite.
(4) Five years: Launch the space station, position it in its assigned
orbital location, and operate it in accordance with the station
authorization.
(b) Licensees of non-geostationary orbit satellite systems other than
DBS and DARS satellite systems licensed on or after September 11, 2003,
will be required to comply with the schedule set forth in paragraphs
(b)(1) through (b)(5) of this section in implementing their satellite
systems, unless a different schedule is established by Title 47,
Chapter I, or by Commission Order, or by Order adopted pursuant to
delegated authority. These dates are to be measured from the date the
license is issued.
(1) One year: Enter into a binding non-contingent contract to construct
the licensed satellite system.
(2) Two years: Complete the critical design review of the licensed
satellite system.
(3) Two years, six months: Begin the construction of the first
satellite in the licensed satellite system.
(4) Three years, six months: Launch the first space station, place it
in the authorized orbit, and operate it in accordance with the station
authorization.
(5) Six years: Bring all the satellites in the licensed satellite
system into operation.
(c) Licensees of all satellite systems, other than DBS and DARS
satellite systems, must either submit a copy of a binding
non-contingent satellite construction contract with the Commission or
notify the Commission in writing that they have not entered into such a
contract, no later than 15 days after the milestone date for entering
into such a contract.
(d) Licensees of all satellite systems, other than DBS and DARS
satellite systems, must either submit information to the Commission
sufficient to demonstrate that the licensee has completed the critical
design review of the licensed satellite system or notify the Commission
in writing that critical design review has not been completed, no later
than 15 days after the milestone date for completion of such design
review.
(e) Licensees of all satellite systems, other than DBS and DARS
satellite systems, must either submit information to the Commission
sufficient to demonstrate that the licensee has commenced physical
construction of its licensed spacecraft or notify the Commission in
writing that such construction has not commenced, no later than 15 days
after the milestone date for such commencement.
(f) Licensees of all satellite systems, other than DBS and SDARS
systems, must either demonstrate compliance with an applicable deadline
for operation or launch and operation specified in paragraph (a) or (b)
of this section or notify the Commission in writing that launch and
commencement of operation has not occurred, no later than 15 days after
the deadline. Compliance with a milestone requirement in paragraph
(a)(4), (b)(4), or (b)(5) of this section may be demonstrated by
certifying pursuant to § 25.121(d) that the space station, or stations,
has, or have, been launched and placed in the authorized orbital
location or non-geostationary orbit(s) and that in-orbit operation of
the space station or stations has been tested and found to be
consistent with the terms of the authorization.
(g) Licensees of satellite systems that include both non-geostationary
orbit satellites and geostationary orbit satellites, other than DBS and
DARS satellite systems, will be required to comply with the schedule in
paragraph (a) of this section with respect to the geostationary orbit
satellites, and with the schedule set forth in paragraph (b) of this
section with respect to the non-geostationary orbit satellites.
(h) In cases where the Commission grants a satellite authorization in
different stages, such as a license for a satellite system using feeder
links or inter-satellite links, the earliest of the milestone schedules
will be applied to the entire satellite system.
[ 68 FR 51507 , Aug. 27, 2003, as amended at 69 FR 51587 , Aug. 20, 2004;
79 FR 8320 , Feb. 12, 2014]
return arrow Back to Top
Goto Section: 25.163 | 25.165
Goto Year: 2013 |
2015
CiteFind - See documents on FCC website that
cite this rule
Want to support this service?
Thanks!
Report errors in
this rule. Since these rules are converted to HTML by machine, it's possible errors have been made. Please
help us improve these rules by clicking the Report FCC Rule Errors link to report an error.
hallikainen.com
Helping make public information public