FCC 25.133
Revised as of October 2, 2015
Goto Year:2014 |
2016
§ 25.133 Period of construction; certification of commencement of operation.
(a)(1) Each initial license for an earth station governed by this part,
except for blanket licenses, will specify as a condition therein the period
in which construction of facilities must be completed and station operation
commenced. Construction of the earth station must be completed and the
station must be brought into operation within 12 months from the date of the
license grant except as may be determined by the Commission for any
particular application.
(2) Each initial blanket license for multiple earth stations at unspecified
locations will specify as a condition therein the period in which station
operation must be commenced. The networks in which the mobile earth stations
will be operated must be brought into operation within 12 months from the
date of the license grant except as may be determined by the Commission for
any particular application.
(b)(1) Each initial license for a transmitting earth station or modified
license authorizing operation of an additional transmitting antenna, except
for blanket licenses, will also specify as a condition therein that upon
completion of construction, the licensee must file with the Commission a
certification containing the following information:
(i) The name of the licensee;
(ii) File number of the application;
(iii) Call sign of the antenna;
(iv) Date of the license;
(v) A certification that the facility as authorized has been completed and
that each antenna has been tested and found to perform within 2 dB of the
applicable pattern specified in § 25.209 or other authorized pattern;
(vi) The date on which the earth station became operational; and
(vii) A statement that the station will remain operational during the
license period unless the license is submitted for cancellation.
(2) For earth stations authorized under any blanket licensing provision in
this chapter, a certification containing the information in paragraph (b)(1)
of this section must be filed when the network is put into operation.
(c) If the facility does not meet the technical parameters set forth in
§ 25.209, a request for a waiver must be submitted and approved by the
Commission before operations may commence.
(d) Each receiving earth station licensed or registered pursuant to § 25.131
must be constructed and placed into service within 6 months after
coordination has been completed. Each licensee or registrant must file with
the Commission a certification that the facility is completed and operating
as provided in paragraph (b) of this section, with the exception of
certification of antenna patterns.
[ 56 FR 24016 , May 28, 1991, as amended at 58 FR 68059 , Dec. 23, 1993; 59 FR 53327 , Oct. 21, 1994; 65 FR 59142 , Oct. 4, 2000; 70 FR 32254 , June 2, 2005;
78 FR 8421 , Feb. 6, 2013; 79 FR 8318 , Feb. 12, 2014]
return arrow Back to Top
Goto Section: 25.132 | 25.134
Goto Year: 2014 |
2016
CiteFind - See documents on FCC website that
cite this rule
Want to support this service?
Thanks!
Report errors in
this rule. Since these rules are converted to HTML by machine, it's possible errors have been made. Please
help us improve these rules by clicking the Report FCC Rule Errors link to report an error.
hallikainen.com
Helping make public information public