FCC 27.14
Revised as of October 1, 2018
Goto Year:2017 |
2019
§ 27.14 Construction requirements.
(a) AWS and WCS licensees, with the exception of WCS licensees holding
authorizations for the 600 MHz band, Block A in the 698-704 MHz and
728-734 MHz bands, Block B in the 704-710 MHz and 734-740 MHz bands,
Block E in the 722-728 MHz band, Block C, C1 or C2 in the 746-757 MHz
and 776-787 MHz bands, Block A in the 2305-2310 MHz and 2350-2355 MHz
bands, Block B in the 2310-2315 MHz and 2355-2360 MHz bands, Block C in
the 2315-2320 MHz band, and Block D in the 2345-2350 MHz band, and with
the exception of licensees holding AWS authorizations in the 1915-1920
MHz and 1995-2000 MHz bands, the 2000-2020 MHz and 2180-2200 MHz bands,
or 1695-1710 MHz, 1755-1780 MHz and 2155-2180 MHz bands, must, as a
performance requirement, make a showing of “substantial service” in
their license area within the prescribed license term set forth in
§ 27.13. “Substantial service” is defined as service which is sound,
favorable and substantially above a level of mediocre service which
just might minimally warrant renewal. Failure by any licensee to meet
this requirement will result in forfeiture of the license and the
licensee will be ineligible to regain it.
(b)-(d) [Reserved]
(e) Comparative renewal proceedings do not apply to WCS licensees
holding authorizations for Block A in the 698-704 MHz and 728-734 MHz
bands, Block B in the 704-710 MHz and 734-740 MHz bands, Block C in the
710-716 MHz and 740-746 MHz bands, Block D in the 716-722 MHz band,
Block E in the 722-728 MHz band, or Block C, C1 or C2 in the 746-757
MHz and 776-787 MHz bands. Each of these licensees must file a renewal
application in accordance with the provisions set forth in § 1.949, and
must make a showing of substantial service, independent of its
performance requirements, as a condition for renewal at the end of each
license term.
(f) [Reserved]
(g) WCS licensees holding EA authorizations for Block A in the 698-704
MHz and 728-734 MHz bands, cellular market authorizations for Block B
in the 704-710 MHz and 734-740 MHz bands, or EA authorizations for
Block E in the 722-728 MHz band, if the results of the first auction in
which licenses for such authorizations are offered satisfy the reserve
price for the applicable block, shall provide signal coverage and offer
service over at least 35 percent of the geographic area of each of
their license authorizations no later than June 13, 2013 (or within
four years of initial license grant if the initial authorization in a
market is granted after June 13, 2009), and shall provide such service
over at least 70 percent of the geographic area of each of these
authorizations by the end of the license term. In applying these
geographic benchmarks, licensees are not required to include land owned
or administered by government as a part of the relevant service area.
Licensees may count covered government land for purposes of meeting
their geographic construction benchmark, but are required to add the
covered government land to the total geographic area used for
measurement purposes. Licensees are required to include those populated
lands held by tribal governments and those held by the Federal
Government in trust or for the benefit of a recognized tribe.
(1) If an EA or CMA licensee holding an authorization in these
particular blocks fails to provide signal coverage and offer service
over at least 35 percent of the geographic area of its license
authorization by no later than June 13, 2013 (or within four years of
initial license grant, if the initial authorization in a market is
granted after June 13, 2009), the term of that license authorization
will be reduced by two years and such licensee may be subject to
enforcement action, including forfeitures. In addition, an EA or CMA
licensee that provides signal coverage and offers service at a level
that is below this interim benchmark may lose authority to operate in
part of the remaining unserved areas of the license.
(2) If any such EA or CMA licensee fails to provide signal coverage and
offer service to at least 70 percent of the geographic area of its
license authorization by the end of the license term, that licensee's
authorization will terminate automatically without Commission action
for those geographic portions of its license in which the licensee is
not providing service, and those unserved areas will become available
for reassignment by the Commission. Such licensee may also be subject
to enforcement action, including forfeitures. In addition, an EA or CMA
licensee that provides signal coverage and offers service at a level
that is below this end-of-term benchmark may be subject to license
termination. In the event that a licensee's authority to operate in a
license area terminates automatically without Commission action, such
areas will become available for reassignment pursuant to the procedures
in paragraph (j) of this section.
(3) For licenses under paragraph (g) of this section, the geographic
service area to be made available for reassignment must include a
contiguous area of at least 130 square kilometers (50 square miles),
and areas smaller than a contiguous area of at least 130 square
kilometers (50 square miles) will not be deemed unserved.
(h) WCS licensees holding REAG authorizations for Block C in the
746-757 MHz and 776-787 MHz bands or REAG authorizations for Block C2
in the 752-757 MHz and 782-787 MHz bands shall provide signal coverage
and offer service over at least 40 percent of the population in each EA
comprising the REAG license area no later than June 13, 2013 (or within
four years of initial license grant, if the initial authorization in a
market is granted after June 13, 2009), and shall provide such service
over at least 75 percent of the population of each of these EAs by the
end of the license term. For purposes of compliance with this
requirement, licensees should determine population based on the most
recently available U.S. Census Data.
(1) If a licensee holding a Block C authorization fails to provide
signal coverage and offer service over at least 40 percent of the
population in each EA comprising the REAG license area by no later than
June 13, 2013 (or within four years of initial license grant if the
initial authorization in a market is granted after June 13, 2009), the
term of the license authorization will be reduced by two years and such
licensee may be subject to enforcement action, including forfeitures.
In addition, a licensee that provides signal coverage and offers
service at a level that is below this interim benchmark may lose
authority to operate in part of the remaining unserved areas of the
license.
(2) If a licensee holding a Block C authorization fails to provide
signal coverage and offer service over at least 75 percent of the
population in any EA comprising the REAG license area by the end of the
license term, for each such EA that licensee's authorization will
terminate automatically without Commission action for those geographic
portions of its license in which the licensee is not providing service.
Such licensee may also be subject to enforcement action, including
forfeitures. In the event that a licensee's authority to operate in a
license area terminates automatically without Commission action, such
areas will become available for reassignment pursuant to the procedures
in paragraph (j) of this section. In addition, a REAG licensee that
provides signal coverage and offers service at a level that is below
this end-of-term benchmark within any EA may be subject to license
termination within that EA.
(3) For licenses under paragraph (h), the geographic service area to be
made available for reassignment must include a contiguous area of at
least 130 square kilometers (50 square miles), and areas smaller than a
contiguous area of at least 130 square kilometers (50 square miles)
will not be deemed unserved.
(i) WCS licensees holding EA authorizations for Block A in the 698-704
MHz and 728-734 MHz bands, cellular market authorizations for Block B
in the 704-710 MHz and 734-740 MHz bands, or EA authorizations for
Block E in the 722-728 MHz band, if the results of the first auction in
which licenses for such authorizations in Blocks A, B, and E are
offered do not satisfy the reserve price for the applicable block, as
well as EA authorizations for Block C1 in the 746-752 MHz and 776-782
MHz bands, are subject to the following:
(1) If a licensee holding a cellular market area or EA authorization
subject to this paragraph (i) fails to provide signal coverage and
offer service over at least 40 percent of the population in its license
area by no later than June 13, 2013 (or within four years of initial
license grant, if the initial authorization in a market is granted
after June 13, 2009), the term of that license authorization will be
reduced by two years and such licensee may be subject to enforcement
action, including forfeitures. In addition, such licensee that provides
signal coverage and offers service at a level that is below this
interim benchmark may lose authority to operate in part of the
remaining unserved areas of the license. For purposes of compliance
with this requirement, licensees should determine population based on
the most recently available U.S. Census Data.
(2) If a licensee holding a cellular market area or EA authorization
subject to this paragraph (i) fails to provide signal coverage and
offer service over at least 75 percent of the population in its license
area by the end of the license term, that licensee's authorization will
terminate automatically without Commission action for those geographic
portions of its license in which the licensee is not providing service,
and those unserved areas will become available for reassignment by the
Commission. Such licensee may also be subject to enforcement action,
including forfeitures. In the event that a licensee's authority to
operate in a license area terminates automatically without Commission
action, such areas will become available for reassignment pursuant to
the procedures in paragraph (j) of this section. In addition, such a
licensee that provides signal coverage and offers service at a level
that is below this end-of-term benchmark may be subject to license
termination. For purposes of compliance with this requirement,
licensees should determine population based on the most recently
available U.S. Census Data.
(3) For licenses under paragraph (i), the geographic service area to be
made available for reassignment must include a contiguous area of at
least 130 square kilometers (50 square miles), and areas smaller than a
contiguous area of at least 130 square kilometers (50 square miles)
will not be deemed unserved.
(j) In the event that a licensee's authority to operate in a license
area terminates automatically under paragraphs (g), (h), or (i) of this
section, such areas will become available for reassignment pursuant to
the following procedures:
(1) The Wireless Telecommunications Bureau is delegated authority to
announce by public notice that these license areas will be made
available and establish a 30-day window during which third parties may
file license applications to serve these areas. During this 30-day
period, licensees that had their authority to operate terminate
automatically for unserved areas may not file applications to provide
service to these areas. Applications filed by third parties that
propose areas overlapping with other applications will be deemed
mutually exclusive, and will be resolved through an auction. The
Wireless Telecommunications Bureau, by public notice, may specify a
limited period before the filing of short-form applications (FCC Form
175) during which applicants may enter into a settlement to resolve
their mutual exclusivity, subject to the provisions of § 1.935 of this
chapter.
(2) Following this 30-day period, the original licensee and third
parties can file license applications for remaining unserved areas
where licenses have not been issued or for which there are no pending
applications. If the original licensee or a third party files an
application, that application will be placed on public notice for 30
days. If no mutually exclusive application is filed, the application
will be granted, provided that a grant is found to be in the public
interest. If a mutually exclusive application is filed, it will be
resolved through an auction. The Wireless Telecommunications Bureau, by
public notice, may specify a limited period before the filing of
short-form applications (FCC Form 175) during which applicants may
enter into a settlement to resolve their mutual exclusivity, subject to
the provisions of § 1.935 of this chapter.
(3) The licensee will have one year from the date the new license is
issued to complete its construction and provide signal coverage and
offer service over 100 percent of the geographic area of the new
license area. If the licensee fails to meet this construction
requirement, its license will automatically terminate without
Commission action and it will not be eligible to apply to provide
service to this area at any future date.
(k) Licensees holding WCS or AWS authorizations in the spectrum blocks
enumerated in paragraphs (g), (h), (i), (q), (r), (s), and (t) of this
section, including any licensee that obtained its license pursuant to
the procedures set forth in paragraph (j) of this section, shall
demonstrate compliance with performance requirements by filing a
construction notification with the Commission, within 15 days of the
expiration of the applicable benchmark, in accordance with the
provisions set forth in § 1.946(d) of this chapter. The licensee must
certify whether it has met the applicable performance requirements. The
licensee must file a description and certification of the areas for
which it is providing service. The construction notifications must
include electronic coverage maps, supporting technical documentation
and any other information as the Wireless Telecommunications Bureau may
prescribe by public notice.
(l) WCS licensees holding authorizations in the spectrum blocks
enumerated in paragraphs (g), (h), or (i) of this section, excluding
any licensee that obtained its license pursuant to the procedures set
forth in subsection (j) of this section, shall file reports with the
Commission that provide the Commission, at a minimum, with information
concerning the status of their efforts to meet the performance
requirements applicable to their authorizations in such spectrum blocks
and the manner in which that spectrum is being utilized. The
information to be reported will include the date the license term
commenced, a description of the steps the licensee has taken toward
meeting its construction obligations in a timely manner, including the
technology or technologies and service(s) being provided, and the areas
within the license area in which those services are available. Each of
these licensees shall file its first report with the Commission no
later than June 13, 2011 and no sooner than 30 days prior to this date.
Each licensee that meets its interim benchmarks shall file a second
report with the Commission no later than June 13, 2016 and no sooner
than 30 days prior to this date. Each licensee that does not meet its
interim benchmark shall file this second report no later than on June
13, 2015 and no sooner than 30 days prior to this date.
(m)-(n) [Reserved]
(o) BRS and EBS licensees originally issued a BRS or EBS license prior
to November 6, 2009 must make a showing of substantial service no later
than May 1, 2011. With respect to initial BRS licenses issued on or
after November 6, 2009, the licensee must make a showing of substantial
service within four years from the date of issue of the license.
Incumbent BRS licensees that are required to demonstrate substantial
service by May 1, 2011 must file their substantial service showings
with their renewal applications. “Substantial service” is defined as
service which is sound, favorable, and substantially above a level of
mediocre service which just might minimally warrant renewal.
Substantial service for BRS and EBS licensees is satisfied if a
licensee meets the requirements of paragraph (o)(1), (o)(2), or (o)(3)
of this section. If a licensee has not met the requirements of
paragraph (o)(1), (o)(2), or (o)(3) of this section, then demonstration
of substantial service shall proceed on a case-by-case basis. Except as
provided in paragraphs (o)(4) and (o)(5) of this section, all
substantial service determinations will be made on a license-by-license
basis. Failure by any licensee to demonstrate substantial service will
result in forfeiture of the license and the licensee will be ineligible
to regain it.
(1) A BRS or EBS licensee has provided “substantial service” by:
(i) Constructing six permanent links per one million people for
licensees providing fixed point-to-point services;
(ii) Providing coverage of at least 30 percent of the population of the
licensed area for licensees providing mobile services or fixed
point-to-multipoint services;
(iii) Providing service to “rural areas” (a county (or equivalent) with
a population density of 100 persons per square mile or less, based upon
the most recently available Census data) and areas with limited access
to telecommunications services:
(A) For mobile service, where coverage is provided to at least 75% of
the geographic area of at least 30% of the rural areas within its
service area; or
(B) for fixed service, where the BRS or EBS licensee has constructed at
least one end of a permanent link in at least 30% of the rural areas
within its licensed area.
(iv) Providing specialized or technologically sophisticated service
that does not require a high level of coverage to benefit consumers; or
(v) Providing service to niche markets or areas outside the areas
served by other licensees.
(2) An EBS licensee has provided “substantial service” when:
(i) The EBS licensee is using its spectrum (or spectrum to which the
EBS licensee's educational services are shifted) to provide educational
services within the EBS licensee's GSA;
(ii) the EBS licensee's license is actually being used to serve the
educational mission of one or more accredited public or private
schools, colleges or universities providing formal educational and
cultural development to enrolled students; or
(iii) the level of service provided by the EBS licensee meets or
exceeds the minimum usage requirements specified in § 27.1214.
(3) An EBS or BRS licensee may be deemed to provide substantial service
through a leasing arrangement if the lessee is providing substantial
service under paragraph (o)(1) of this section. The EBS licensee must
also be otherwise in compliance with this Chapter (including the
programming requirements in § 27.1203 of this subpart).
(4) If the GSA of a licensee is less than 1924 square miles in size,
and there is an overlapping co-channel station licensed or leased by
the licensee or its affiliate, substantial service may be demonstrated
by meeting the requirements of paragraph (o)(1) or (o)(2) of this
section with respect to the combined GSAs of both stations.
(5) If the GSA of a BTA authorization holder, is less than one-half of
the area within the BTA for every BRS channel, substantial service may
be demonstrated for the licenses in question by meeting the
requirements of paragraph (o)(1) or (o)(2) of this section with respect
to the combined GSAs of the BTA authorization holder, together with any
incumbent authorizations licensed or leased by the licensee or its
affiliates.
(p) This section enumerates performance requirements for licensees
holding authorizations for Block A in the 2305-2310 MHz and 2350-2355
MHz bands, Block B in the 2310-2315 MHz and 2355-2360 MHz bands, Block
C in the 2315-2320 MHz band, and Block D in the 2345-2350 MHz band.
(1) For mobile and point-to-multipoint systems in Blocks A and B, and
point-to-multipoint systems in Blocks C and D, a licensee must provide
reliable signal coverage and offer service to at least 40 percent of
the license area's population by March 13, 2017, and to at least 75
percent of the license area's population by September 13, 2019. If,
when filing the construction notification required under § 1.946(d) of
this chapter, a WCS licensee demonstrates that 25 percent or more of
the license area's population for Block A, B or D is within a
coordination zone as defined by § 27.73(a) of the rules, the foregoing
population benchmarks are reduced to 25 and 50 percent, respectively.
The percentage of a license area's population within a coordination
zone equals the sum of the Census Block Centroid Populations within the
area, divided by the license area's total population.
(2) For point-to-point fixed systems, except those deployed in the Gulf
of Mexico license area, a licensee must construct and operate a minimum
of 15 point-to-point links per million persons (one link per 67,000
persons) in a license area by March 13, 2017, and 30 point-to-point
links per million persons (one link per 33,500 persons) in a licensed
area by September 13, 2019. The exact link requirement is calculated by
dividing a license area's total population by 67,000 and 33,500 for the
respective milestones, and then rounding upwards to the next whole
number. For a link to be counted towards these benchmarks, both of its
endpoints must be located in the license area. If only one endpoint of
a link is located in a license area, it can be counted as a one- half
link towards the benchmarks.
(3) For point-to-point fixed systems deployed on any spectrum block in
the Gulf of Mexico license area, a licensee must construct and operate
a minimum of 15 point-to-point links by March 13, 2017, and a minimum
of 15 point-to-point links by September 13, 2019.
(4) Under paragraph (p)(2) and (p)(3) of this section, each fixed link
must provide a minimum bit rate, in bits per second, equal to or
greater than the bandwidth specified by the emission designator in
Hertz (e.g., equipment transmitting at a 5 Mb/s rate must not require a
bandwidth of greater than 5 MHz).
(5) If an initial authorization for a license area is granted after
March 13, 2013, then the applicable benchmarks in paragraphs (p)(1),
(2) and (3) of this section must be met within 48 and 78 months,
respectively, of the initial authorization grant date.
(6) Licensees must use the most recently available U.S. Census Data at
the time of measurement to meet these performance requirements.
(7) Licensees must certify compliance with the applicable performance
requirements by filing a construction notification with the Commission,
within 15 days of the expiration of the relevant performance milestone,
pursuant to § 1.946(d) of this chapter. Each construction notification
must include electronic coverage maps, supporting technical
documentation, and any other information as the Wireless
Telecommunications Bureau may prescribe by public notice. Electronic
coverage maps must accurately depict the boundaries of each license
area (Regional Economic Area Grouping, REAG, or Major Economic Area,
MEA) in the licensee's service territory. Further, REAG maps must
depict MEA boundaries and MEA maps must depict Economic Area
boundaries. If a licensee does not provide reliable signal coverage to
an entire license area, its map must accurately depict the boundaries
of the area or areas within each license area not being served. Each
licensee also must file supporting documentation certifying the type of
service it is providing for each REAG or MEA within its service
territory and the type of technology used to provide such service.
Supporting documentation must include the assumptions used to create
the coverage maps, including the propagation model and the signal
strength necessary to provide reliable service with the licensee's
technology.
(8) If a licensee fails to meet any applicable performance requirement,
its authorization will terminate automatically without further
Commission action as of the applicable performance milestone and the
licensee will be ineligible to regain it.
(q) The following provisions apply to any licensee holding an AWS
authorization in the 2000-2020 MHz and 2180-2200 MHz bands (an “AWS-4
licensee”):
(1) An AWS-4 licensee shall provide terrestrial signal coverage and
offer terrestrial service within four (4) years from the date of the
license to at least forty (40) percent of the total population in the
aggregate service areas that it has licensed in the 2000-2020 MHz and
2180-2200 MHz bands (“AWS-4 Interim Buildout Requirement”). For
purposes of this subpart, a licensee's total population shall be
calculated by summing the population of each license area that a
licensee holds in the 2000-2020 MHz and 2180-2200 MHz bands; and
(2) An AWS-4 licensee shall provide terrestrial signal coverage and
offer terrestrial service within seven (7) years from the date of the
license to at least seventy (70) percent of the population in each of
its license areas in the 2000-2020 MHz and 2180-2200 MHz bands (“AWS-4
Final Buildout Requirement”).
(3) If any AWS-4 licensee fails to establish that it meets the AWS-4
Interim Buildout Requirement, the AWS-4 Final Buildout requirement
shall be accelerated by one year from (seven to six years).
(4) If any AWS-4 licensee fails to establish that it meets the AWS-4
Final Buildout Requirement in any of its license areas in the 2000-2020
MHz and 2180-2200 MHz bands, its authorization for each license area in
which it fails to meet the requirement shall terminate automatically
without Commission action. To the extent that the AWS-4 licensee also
holds the 2 GHz MSS rights for the affected license area, failure to
meet the AWS-4 Final Buildout Requirement in an EA shall also result in
the MSS protection rule in § 27.1136 no longer applying in that license
area.
(5) To demonstrate compliance with these performance requirements,
licensees shall use the most recently available U.S. Census Data at the
time of measurement and shall base their measurements of population
served on areas no larger than the Census Tract level. The population
within a specific Census Tract (or other acceptable identifier) will
only be deemed served by the licensee if it provides signal coverage to
and offers service within the specific Census Tract (or other
acceptable identifier). To the extent the Census Tract (or other
acceptable identifier) extends beyond the boundaries of a license area,
a licensee with authorizations for such areas may only include the
population within the Census Tract (or other acceptable identifier)
towards meeting the performance requirement of a single, individual
license.
(6) Failure by any AWS-4 licensee to meet the AWS-4 Final Buildout
Requirement in paragraph (q)(4) of this section will result in
forfeiture of the license and the licensee will be ineligible to regain
it.
(7) Renewal showing. An applicant for renewal of a geographic-area
authorization in the 2000-2020 MHz and 2180-2200 MHz service bands must
make a renewal showing, independent of its performance requirements, as
a condition of renewal. The showing must include a detailed description
of the applicant's provision of service during the entire license
period and address:
(i) The level and quality of service provided by the applicant
(including the population served, the area served, the number of
subscribers, the services offered);
(ii) The date service commenced, whether service was ever interrupted,
and the duration of any interruption or outage;
(iii) The extent to which service is provided to rural areas;
(iv) The extent to which service is provided to qualifying tribal land
as defined in § 1.2110(f)(3)(i) of this chapter; and
(v) Any other factors associated with the level of service to the
public.
(r) The following provisions apply to any licensee holding an AWS
authorization in the 1915-1920 MHz and 1995-2000 MHz bands:
(1) A licensee shall provide signal coverage and offer service within
four (4) years from the date of the initial license to at least forty
(40) percent of the population in each of its licensed areas (“Interim
Buildout Requirement”).
(2) A licensee shall provide signal coverage and offer service within
ten (10) years from the date of the initial license to at least
seventy-five (75) percent of the population in each of its licensed
areas (“Final Buildout Requirement”).
(3) If a licensee fails to establish that it meets the Interim Buildout
Requirement for a particular licensed area, then the Final Buildout
Requirement (in this paragraph (r)) and the license term (as set forth
in § 27.13(j)) for each license area in which it fails to meet the
Interim Buildout Requirement shall be accelerated by two years (from
ten to eight years).
(4) If a licensee fails to establish that it meets the Final Buildout
Requirement for a particular licensed area, its authorization for each
license area in which it fails to meet the Final Buildout Requirement
shall terminate automatically without Commission action and the
licensee will be ineligible to regain it if the Commission makes the
license available at a later date.
(5) To demonstrate compliance with these performance requirements,
licensees shall use the most recently available U.S. Census Data at the
time of measurement and shall base their measurements of population
served on areas no larger than the Census Tract level. The population
within a specific Census Tract (or other acceptable identifier) will
only be deemed served by the licensee if it provides signal coverage to
and offers service within the specific Census Tract (or other
acceptable identifier). To the extent the Census Tract (or other
acceptable identifier) extends beyond the boundaries of a license area,
a licensee with authorizations for such areas may only include the
population within the Census Tract (or other acceptable identifier)
towards meeting the performance requirement of a single, individual
license.
(6) An applicant for renewal of a license covered by this paragraph (r)
must make a renewal showing, independent of its performance
requirements, as a condition of renewal. The showing must include a
detailed description of the applicant's provision of service during the
entire license period and address:
(i) The level and quality of service provided by the applicant
(including the population served, the area served, the number of
subscribers, the services offered);
(ii) The date service commenced, whether service was ever interrupted,
and the duration of any interruption or outage;
(iii) The extent to which service is provided to rural areas;
(iv) The extent to which service is provided to qualifying tribal land
as defined in § 1.2110(f)(3)(i) of this chapter; and
(v) Any other factors associated with the level of service to the
public.
(s) The following provisions apply to any licensee holding an AWS
authorization in the 1695-1710 MHz, 1755-1780 MHz, and 2155-2180 MHz
bands:
(1) A licensee shall provide reliable signal coverage and offer service
within six (6) years from the date of the initial license to at least
forty (40) percent of the population in each of its licensed areas
(“Interim Buildout Requirement”).
(2) A licensee shall provide reliable signal coverage and offer service
within twelve (12) years from the date of the initial license to at
least seventy-five (75) percent of the population in each of its
licensed areas (“Final Buildout Requirement”).
(3) If a licensee fails to establish that it meets the Interim Buildout
Requirement for a particular licensed area, then the Final Buildout
Requirement (in this paragraph (s)) and the AWS license term (as set
forth in § 27.13(k)) for each license area in which it fails to meet the
Interim Buildout Requirement shall be accelerated by two (2) years
(from twelve (12) to ten (10) years).
(4) If a licensee fails to establish that it meets the Final Buildout
Requirement for a particular licensed area, its authorization for each
license area in which it fails to meet the Final Buildout Requirement
shall terminate automatically without Commission action and the
licensee will be ineligible to regain it if the Commission makes the
license available at a later date.
(5) To demonstrate compliance with these performance requirements,
licensees shall use the most recently available U.S. Census Data at the
time of measurement and shall base their measurements of population
served on areas no larger than the Census Tract level. The population
within a specific Census Tract (or other acceptable identifier) will be
deemed served by the licensee only if it provides signal coverage to
and offers service within the specific Census Tract (or other
acceptable identifier). To the extent the Census Tract (or other
acceptable identifier) extends beyond the boundaries of a license area,
a licensee with authorizations for such areas may include only the
population within the Census Tract (or other acceptable identifier)
towards meeting the performance requirement of a single, individual
license. For the Gulf of Mexico license area, the licensee shall
demonstrate compliance with these performance requirements, using
off-shore platforms, including production, manifold, compression,
pumping and valving platforms as a proxy for population in the Gulf of
Mexico.
(6) An applicant for renewal of a license covered by paragraph (s) of
this section must make a renewal showing, independent of its
performance requirements, as a condition of each renewal. The showing
must include a detailed description of the applicant's provision of
service during the entire license period and address:
(i) The level and quality of service provided by the applicant
(including the population served, the area served, the number of
subscribers, the services offered);
(ii) The date service commenced, whether service was ever interrupted,
and the duration of any interruption or outage;
(iii) The extent to which service is provided to rural areas;
(iv) The extent to which service is provided to qualifying tribal land
as defined in § 1.2110(f)(3)(i) of this chapter; and
(v) Any other factors associated with the level of service to the
public.
(t) The following provisions apply to any licensee holding an
authorization in the 600 MHz band:
(1) A licensee shall provide reliable signal coverage and offer service
within six (6) years from the date of the initial license to at least
forty (40) percent of the population in each of its license areas
(“Interim Buildout Requirement”).
(2) A licensee shall provide reliable signal coverage and offer service
within twelve (12) years from the date of the initial license to at
least seventy-five (75) percent of the population in each of its
license areas (“Final Buildout Requirement”).
(3) If a licensee fails to establish that it meets the Interim Buildout
Requirement for a particular licensed area, then the Final Buildout
Requirement (in this paragraph (t)) and the license term (as set forth
in § 27.13(l)) for each license area in which it fails to meet the
Interim Buildout Requirement shall be accelerated by two (2) years
(from twelve (12) to ten (10) years).
(4) If a licensee fails to establish that it meets the Final Buildout
Requirement for a particular license area, its authorization for each
license area in which it fails to meet the Final Buildout Requirement
shall terminate automatically without Commission action, and the
licensee will be ineligible to regain it if the Commission makes the
license available at a later date.
(5) To demonstrate compliance with these performance requirements,
licensees shall use the most recently available decennial U.S. Census
Data at the time of measurement and shall base their measurements of
population served on areas no larger than the Census Tract level. The
population within a specific Census Tract (or other acceptable
identifier) will be deemed served by the licensee only if it provides
reliable signal coverage to and offers service within the specific
Census Tract (or other acceptable identifier). To the extent the Census
Tract (or other acceptable identifier) extends beyond the boundaries of
a license area, a licensee with authorizations for such areas may
include only the population within the Census Tract (or other
acceptable identifier) towards meeting the performance requirement of a
single, individual license. For the Gulf of Mexico license area, the
licensee shall demonstrate compliance with these performance
requirements, using off-shore platforms, including production,
manifold, compression, pumping and valving platforms as a proxy for
population in the Gulf of Mexico.
(6) An applicant for renewal of a license covered by this paragraph (t)
must make a renewal showing, independent of its performance
requirements, as a condition of each renewal. The showing must include
a detailed description of the applicant's provision of service during
the entire license period and address:
(i) The level and quality of service provided by the applicant
(including the population served, the area served, the number of
subscribers, the services offered);
(ii) The date service commenced, whether service was ever interrupted,
and the duration of any interruption or outage;
(iii) The extent to which service is provided to rural areas;
(iv) The extent to which service is provided to qualifying tribal land
as defined in § 1.2110(f)(3)(i) of this chapter; and
(v) Any other factors associated with the level of service to the
public.
[ 62 FR 9658 , Mar. 3, 1997]
Editorial Note: For Federal Register citations affecting § 27.14, see
the List of CFR Sections Affected, which appears in the Finding Aids
section of the printed volume and at www.fdsys.gov.
Effective Date Note: At 82 FR 41548 , Sept. 1, 2017, § 27.14 was amended
by removing paragraphs (e), (q)(7), (r)(6), (s)(6), and (t)(6). These
paragraphs contain information collection and recordkeeping
requirements and the removals will not become effective until approval
has been given by the Office of Management and Budget.
return arrow Back to Top
Goto Section: 27.13 | 27.15
Goto Year: 2017 |
2019
CiteFind - See documents on FCC website that
cite this rule
Want to support this service?
Thanks!
Report errors in
this rule. Since these rules are converted to HTML by machine, it's possible errors have been made. Please
help us improve these rules by clicking the Report FCC Rule Errors link to report an error.
hallikainen.com
Helping make public information public